Asphalt Resurfacing of Various City Streets

A regular program of road resurfacing is necessary to prevent City maintained roads from deteriorating to the point where reconstruction is necessary.

The City’s Pavement Management System is designed to evaluate City streets and determine the appropriate preventive maintenance measure.  This approach is proven to be the most efficient and cost effective in pavement management, and one which will have a lasting effect.

During the resurfacing operation, maintenance of traffic will be in place to route vehicular traffic safely around the work zone. Please drive with caution when traveling in these areas.

PROJECT TIMELINE

  • Mitchell Hammock Road – April 4th to April 30th (night work)
  • Norma Ave / Clonts Street / Whispering Woods - April 19th to April 30th (day work)
  • S Lake Jessup Ave / Garden Street / Milton Square - April 26th to May 7th (day work)
  • Kingsbridge East / Waverlee Woods - May 3rd to May 14th (day work)
  • Live Oak Reserve Blvd - May 10th to May 21st (day work)

These timelines are approximate and may change due to weather or other unforeseen events.

Asphalt Resurfacing